District 7 Town Hall Series: City of Coconut Creek

May 19, 2021 | 6:00 PM

The District 7 Town Hall Series kicked off with the City of Coconut Creek on Wednesday, May 19, 2021. Updates about the SMART Program projects at each school within the city were provided by the SMART Program Management team. Data and visual content regarding both completed and ongoing renovations was provided in the presentation included below:

Click the link to watch the meeting: https://www.eduvision.tv/l?emtytye

When is the SMART Program expected be completed?2021-06-03T15:43:50-04:00

Based on the current schedule, the program is expected to be completed late 2025.

What happens if there is damage to any of the underway or completed roof projects?2021-06-03T15:53:58-04:00

The school district has insurance to cover any damage incurred.

What is the status of completion for Tradewinds Elementary School?2021-06-03T15:55:54-04:00

This school’s forecasted completion date is Q4 2022. Currently, the project is on track for earlier completion due to the existing roofing equipment being in better condition than originally expected.

Why is there no Primary Renovations for Dave Thomas West?2021-06-03T15:23:53-04:00

At the time of the 2014 Needs Assessment, Dave Thomas Center – West was not identified for a primary renovations project.