LAUDERHILL
6-12

PROJECT PHASE

Closeout

Construction

  • Project Planning
  • Hire Designer
  • Project Design
  • Hire Contractor
  • Active Construction
  • Construction Closeout

ALLOCATED BUDGET

  • $7,282,410

PHASE 1

  • Fire Alarm
  • Fire Sprinklers
  • HVAC Improvements
  • Media Center Improvements
  • Building Envelope Improvements

PHASE 2

  • Kitchen HVAC

PHASE 3

  • Roofing

TARGETED COMPLETION

(Calendar Year)

  • P1: Q1 2025 | P2: Q3 2023 | P3: Q2 2024

Original Schedule: Q4 2019 | 2018 Schedule: Q1 2021

Preparing campus to begin construction.

ADDITIONAL PROJECT REPORTING

As part of the School Choice Enhancement Program (SCEP), schools are allocated $100,000 to spend on customized enhancements voted on by the school and its community. Common uses of the funds include laptops, security enhancements, projectors, and other useful educational tools.

Listed below are some of the items this school has ordered through SCEP:

COMPLETE

All items delivered

  • Crowd control items

  • Stools

  • Gym scoreboards & gym bleachers
  • Chairs
  • Combination chairs/desks

  • Crowd control items

  • Stools
  • Gym scoreboards & gym bleachers
  • Chairs
  • Combination chairs/desks

WANT TO LEARN MORE ABOUT THE SMART PROGRAM?

The SMART Program is enhancing over 200 schools all across Broward County, and you’ve helped to make it happen!

To find out more about projects like this one, the planning involved, and your role in the history of this Bond, click below or email the SMARTĀ Team.

WANT TO LEARN MORE ABOUT THE SMART PROGRAM?

The SMART Program is enhancing over 200 schools all across Broward County, and you’ve helped to make it happen!

To find out more about projects like this one, the planning involved, and your role in the history of this Bond, click below or email the SMARTĀ Team.