Project Description
SANDERS PARK
ELEMENTARY SCHOOL
PROJECT PHASE

ALLOCATED BUDGET
$9,740,994
SCOPE OF WORK
- Building Envelope Improvements
- Fire Alarm
- Fire Sprinklers
- HVAC Improvements
- Media Center Improvements
TARGETED COMPLETION
(Calendar Year)
Q3 2025
Original Schedule: Q4 2020 | 2018 Schedule: Q1 2022
Contractors are currently preparing the campus for construction.
SANDERS PARK
ELEMENTARY SCHOOL
PROJECT PHASE
ALLOCATED BUDGET
$5,079,000
SCOPE OF WORK
- Building Envelope Improvements
- Fire Alarm
- Fire Sprinklers
- HVAC Improvements
- Media Center Improvements
TARGETED COMPLETION
(Calendar Year)
Q4 2025
Original Schedule: Q4 2020 | 2018 Schedule: Q1 2022
THE SCHOOL IS IN THE PROCESS OF HIRING A CONTRACTOR TO COMPLETE ITS RENOVATIONS.

As part of the School Choice Enhancement Program (SCEP), schools are allocated $100,000 to spend on customized enhancements voted on by the school and its community. Common uses of the funds include laptops, security enhancements, projectors, and other useful educational tools.
Listed below are some of the items this school has ordered through SCEP:
IMPLEMENTATION
IMPLEMENTATION
Marquee
Teachers’ Chairs
Golf Cart
Classroom furniture
Facilities Equipment
Front Office Furniture
Window Wraps
Front Office Furniture
WANT TO LEARN MORE ABOUT THE SMART PROGRAM?
The SMART Program is enhancing over 200 schools all across Broward County, and you’ve helped to make it happen!
To find out more about projects like this one, the planning involved, and your role in the history of this Bond, click below or email the SMARTĀ Team.
WANT TO LEARN MORE ABOUT THE SMART PROGRAM?
The SMART Program is enhancing over 200 schools all across Broward County, and you’ve helped to make it happen!
To find out more about projects like this one, the planning involved, and your role in the history of this Bond, click below or email the SMARTĀ Team.