SANDERS PARK
ELEMENTARY SCHOOL

PROJECT PHASE

ALLOCATED BUDGET

  • $9,740,994

SCOPE OF WORK

  • Building Envelope Improvements
  • Fire Alarm
  • Fire Sprinklers
  • HVAC Improvements
  • Media Center Improvements

TARGETED COMPLETION

(Calendar Year)

  • Q3 2025

Original Schedule: Q4 2020 | 2018 Schedule: Q1 2022

HVAC and Fire Alarm improvements are in progress

SANDERS PARK
ELEMENTARY SCHOOL

PROJECT PHASE

ALLOCATED BUDGET

  • $5,079,000

SCOPE OF WORK

  • Building Envelope Improvements
  • Fire Alarm
  • Fire Sprinklers
  • HVAC Improvements
  • Media Center Improvements

TARGETED COMPLETION

(Calendar Year)

  • Q4 2025

Original Schedule: Q4 2020 | 2018 Schedule: Q1 2022

THE SCHOOL IS IN THE PROCESS OF HIRING A CONTRACTOR TO COMPLETE ITS RENOVATIONS.

ADDITIONAL PROJECT REPORTING

As part of the School Choice Enhancement Program (SCEP), schools are allocated $100,000 to spend on customized enhancements voted on by the school and its community. Common uses of the funds include laptops, security enhancements, projectors, and other useful educational tools.

Listed below are some of the items this school has ordered through SCEP:

IMPLEMENTATION

IMPLEMENTATION

  • Marquee

  • Teachers’ Chairs

  • Golf Cart

  • Classroom furniture

  • Two-way Radio

  • Two-way Radio

  • Poster Maker

  • Facilities Equipment

  • Front Office Furniture

  • Window Wraps

  • Accessories

WANT TO LEARN MORE ABOUT THE SMART PROGRAM?

The SMART Program is enhancing over 200 schools all across Broward County, and you’ve helped to make it happen!

To find out more about projects like this one, the planning involved, and your role in the history of this Bond, click below or email the SMARTĀ Team.

WANT TO LEARN MORE ABOUT THE SMART PROGRAM?

The SMART Program is enhancing over 200 schools all across Broward County, and you’ve helped to make it happen!

To find out more about projects like this one, the planning involved, and your role in the history of this Bond, click below or email the SMARTĀ Team.