Project Description

PLANTATION
HIGH SCHOOL

PROJECT PHASE

ALLOCATED BUDGET

  • $16,783,670

PHASE 1 – PRIMARY RENOVATIONS

  • Building Envelope Improvements
  • Fire Sprinklers
  • HVAC Improvements
  • Media Center Improvements
  • Replace Building 2
  • Safety / Security Upgrade
  • STEM Lab Improvements

PHASE 2 – PRIMARY RENOVATIONS

  • Re-roofing of Building 7

TARGETED COMPLETION

(Calendar Year)

  • P1: Q3 2025 | P2: Q1 2023

Original Schedule: Q1 2020 | 2018 Schedule: Q2 2022

Contractors are currently preparing the campus for construction.

Contractors are currently preparing the campus for construction.

ADDITIONAL PROJECT REPORTING

As part of the School Choice Enhancement Program (SCEP), schools are allocated $100,000 to spend on customized enhancements voted on by the school and its community. Common uses of the funds include laptops, security enhancements, projectors, and other useful educational tools.

Listed below are some of the items this school has ordered through SCEP:

COMPLETE

All Items delivered

  • Golf Cart
  • Front Office Furniture

  • Gym Speaker System

  • Gym Scoreboards
  • Digital Marquee

  • Golf Cart
  • Front Office Furniture

  • Gym Speaker System

  • Gym Scoreboards
  • Digital Marquee

WANT TO LEARN MORE ABOUT THE SMART PROGRAM?

The SMART Program is enhancing over 200 schools all across Broward County, and you’ve helped to make it happen!

To find out more about projects like this one, the planning involved, and your role in the history of this Bond, click below or email the SMARTĀ Team.

UNDERSTANDING THE PROCESS

WANT TO LEARN MORE ABOUT THE SMART PROGRAM?

The SMART Program is enhancing over 200 schools all across Broward County, and you’ve helped to make it happen!

To find out more about projects like this one, the planning involved, and your role in the history of this Bond, click below or email the SMARTĀ Team.

UNDERSTANDING THE PROCESS
SEE MORE SCHOOLS IN THE SMART PROGRAM