PALMVIEW
ELEMENTARY SCHOOL

PROJECT PHASE

Contractor

  • Planning
  • Designer
  • Design
  • Contractor
  • Active Construction
  • Construction Closeout

ALLOCATED BUDGET

  • $3,232,000

SCOPE OF WORK

  • Building Envelope Improvements
  • Fire Sprinklers
  • HVAC Improvements
  • Media Center Improvements

TARGETED COMPLETION

(Calendar Year)

  • Q1 2026

Original Schedule: Q3 2020 | 2018 Schedule: Q1 2022

Primary renovation is in the process of hiring a contractor

Construction drawings are being developed by professional design team. Once complete, a contractor will be hired to begin construction.

ADDITIONAL PROJECT REPORTING

As part of the School Choice Enhancement Program (SCEP), schools are allocated $100,000 to spend on customized enhancements voted on by the school and its community. Common uses of the funds include laptops, security enhancements, projectors, and other useful educational tools.

complete

  • Two-way Radios & Licenses
  • Digital Marquee

  • Morning Show Equipment

  • Printers
  • Technology Accessories

  • TV

  • Tilt Mount
  • Outdoor Furniture

  • TV Install
  • Conference Room Furniture

WANT TO LEARN MORE ABOUT THE SMART PROGRAM?

The SMART Program is enhancing over 200 schools all across Broward County, and you’ve helped to make it happen!

To find out more about projects like this one, the planning involved, and your role in the history of this Bond, click below or email the SMARTĀ Team.

WANT TO LEARN MORE ABOUT THE SMART PROGRAM?

The SMART Program is enhancing over 200 schools all across Broward County, and you’ve helped to make it happen!

To find out more about projects like this one, the planning involved, and your role in the history of this Bond, click below or email the SMARTĀ Team.