Project Description
DRIFTWOOD
ELEMENTARY SCHOOL
PROJECT PHASE
Contractor
ALLOCATED BUDGET
$2,079,685
SCOPE OF WORK
- Building Envelope Improvements
- Fire Sprinklers
HVAC Improvements
TARGETED COMPLETION
(Calendar Year)
Q1 2025
Original Schedule: Q2 2020 | 2018 Schedule: Q2 2021
Construction drawings are being developed by professional design team. Once complete, a contractor will be hired to begin construction.
DRIFTWOOD
ELEMENTARY SCHOOL
PROJECT PHASE
ALLOCATED BUDGET
$2,080,000
SCOPE OF WORK
- Building Envelope Improvements
- Fire Sprinklers
HVAC Improvements
TARGETED COMPLETION
(Calendar Year)
Q1 2025
Original Schedule: Q2 2020 | 2018 Schedule: Q2 2021
Construction drawings are being developed by professional design team. Once complete, a contractor will be hired to begin construction.

As part of the School Choice Enhancement Program (SCEP), schools are allocated $100,000 to spend on customized enhancements voted on by the school and its community. Common uses of the funds include laptops, security enhancements, projectors, and other useful educational tools.
Listed below are some of the items this school has ordered through SCEP:
IMPLEMENTATION
PLANNING/DESIGN
- Indoor Furniture
Promethean Boards
Outdoor Benches
Picnic Tables
ThinkCenters
Projectors
Speakers
Additional intercom speakers on order
WANT TO LEARN MORE ABOUT THE SMART PROGRAM?
The SMART Program is enhancing over 200 schools all across Broward County, and you’ve helped to make it happen!
To find out more about projects like this one, the planning involved, and your role in the history of this Bond, click below or email the SMARTĀ Team.
WANT TO LEARN MORE ABOUT THE SMART PROGRAM?
The SMART Program is enhancing over 200 schools all across Broward County, and you’ve helped to make it happen!
To find out more about projects like this one, the planning involved, and your role in the history of this Bond, click below or email the SMARTĀ Team.