PROJECT PHASE

ALLOCATED BUDGET

  • $17,903,461

PHASE 1

  • Building Envelope Improvements

  • New Building Addition 

  • HVAC Improvements

PHASE 2

  • Re-roofing Building 4

TARGETED COMPLETION

(Calendar Year)

  • Q2 2023

Original Schedule: Q4 2019 I 2018 Schedule: Q4 2019

ADDITIONAL PROJECT REPORTING

As part of the School Choice Enhancement Program (SCEP), schools are allocated $100,000 to spend on customized enhancements voted on by the school and its community. Common uses of the funds include laptops, security enhancements, projectors, and other useful educational tools.

Listed below are some of the items this school has ordered through SCEP:

COMPLETE

All items delivered

  • Hedger
  • Trimmer
  • Digital marquee
  • Blower
  • Two-way radios
  • Office furniture

  • ID machine
  • Recordex
  • Golf carts
  • Two-way radio batteries
  • Hedger
  • Trimmer
  • Digital marquee
  • Blower
  • Two-way radios
  • ID machine
  • Recordex
  • Golf carts
  • Two-way radio batteries
  • Office furniture

WANT TO LEARN MORE ABOUT THE SMART PROGRAM?

The SMART Program is enhancing over 200 schools all across Broward County, and you’ve helped to make it happen!

To find out more about projects like this one, the planning involved, and your role in the history of this Bond, click below or email the SMART Team.

WANT TO LEARN MORE ABOUT THE SMART PROGRAM?

The SMART Program is enhancing over 200 schools all across Broward County, and you’ve helped to make it happen!

To find out more about projects like this one, the planning involved, and your role in the history of this Bond, click below or email the SMART Team.