SILVER LAKES
MIDDLE SCHOOL

PROJECT PHASE

Construction

Construction

  • Planning
  • Designer
  • Design
  • Contractor
  • Active Construction
  • Construction Closeout

ALLOCATED BUDGET

  • $2,930,862

PHASE 1 – PRIMARY RENOVATIONS

  • Building Envelope Improvements
  • Fire Sprinklers
  • Media Center Improvements

PHASE-2

  • Roofing (in construction)

TARGETED COMPLETION

(Calendar Year)

  • Q1 2025

Original Schedule: Q1 2021 | 2018 Schedule: Q4 2022

Reroofing of Buildings 1, 6-15, & 85 is scheduled for completion by 9/9/24.

Construction drawings are being developed by professional design team. Once complete, a contractor will be hired to begin construction.

ADDITIONAL PROJECT REPORTING

As part of the School Choice Enhancement Program (SCEP), schools are allocated $100,000 to spend on customized enhancements voted on by the school and its community. Common uses of the funds include laptops, security enhancements, projectors, and other useful educational tools.

Listed below are some of the items this school has ordered through SCEP:

Complete

IMPLEMENTATION

  • Window Wraps

  • Indoor Furniture

  • Electric strikes

WANT TO LEARN MORE ABOUT THE SMART PROGRAM?

The SMART Program is enhancing over 200 schools all across Broward County, and you’ve helped to make it happen!

To find out more about projects like this one, the planning involved, and your role in the history of this Bond, click below or email the SMARTĀ Team.

WANT TO LEARN MORE ABOUT THE SMART PROGRAM?

The SMART Program is enhancing over 200 schools all across Broward County, and you’ve helped to make it happen!

To find out more about projects like this one, the planning involved, and your role in the history of this Bond, click below or email the SMARTĀ Team.