EVERGLADES
HIGH SCHOOL

PROJECT PHASE

ALLOCATED BUDGET

  • $7,625,580

SCOPE OF WORK

  • Building Envelope Improvements
  • HVAC Improvements

TARGETED COMPLETION

(Calendar Year)

  • Q2 2021

Original Schedule: Q2 2020 | 2018 Schedule: Q3 2021

EVERGLADES
HIGH SCHOOL

PROJECT PHASE

ALLOCATED BUDGET

  • $8,040,254

SCOPE OF WORK

  • Building Envelope Improvements
  • HVAC Improvements

TARGETED COMPLETION

(Calendar Year)

  • Q2 2021

Original Schedule: Q2 2020 | 2018 Schedule: Q3 2021

ADDITIONAL PROJECT REPORTING

As part of the School Choice Enhancement Program (SCEP), schools are allocated $100,000 to spend on customized enhancements voted on by the school and its community. Common uses of the funds include laptops, security enhancements, projectors, and other useful educational tools.

Listed below are some of the items this school has ordered through SCEP:

COMPLETE

All items delivered

  • Laptops

  • Printers

  • Aiphone

  • Strike

Stay up-to-date with the project’s development by visiting its SMART Program gallery, updated regularly with new photos, videos, and other visual content.